Status of Utility Undergrounding Districts

  1. Status of Utility/Ratepayer Financed Underground Utility Districts

     

    1. Grizzly Peak/Summit Utility Underground District No. 48

      Assessment Process Start - May 2014
      Assessment Public Hearing - July 2014 - December 2014
      Assessment Process Complete - January 2015 - June 30, 2015
      Design start - January 2014
      Design completion - December 2015
      Substructure start - July 2015
      Substructure complete - December 2016
      Electric construction start - January 2017
      Pole removal complete - December 2018

    2. Vistamont Utility Underground District No. 35A

      Assessment Process Start - TBD
      Assessment Public Hearing - TBD
      Assessment Process Complete - TBD
      Design start - TBD
      Design completion - TBD
      Substructure start - TBD
      Substructure complete - TBD
      Electric construction start - TBD
      Pole removal complete - TBD

     

  2. Status of Applicant Financed Underground Utility Districts

Applicant Financed Underground Utility District Informational Packets are currently being revised. They are scheduled to be available at a later date.

The moratorium on applications for Utility Underground District will continue indefinitely.