Status of Utility Undergrounding Districts

  1. Status of Utility/Ratepayer Financed Underground Utility Districts

     

    1. Miller/Stevenson Utility Underground District No. 47

      Assessment Process Start - September 2005
      Assessment Public Hearing - June 2006
      Assessment Process Complete - August 2006
      Design start - October 2005
      Design completion - December 2007
      Construction start - February 2008
      Substructure complete - October 2009
      Electric construction start - October 2009
      Construction end - December 2012

    2. Grizzly Peak/Summit Utility Underground District No. 48

      Assessment Process Start - To Be Determined (TBD)
      Assessment Public Hearing - TBD
      Assessment Process Complete - TBD
      Design start - January 2013
      Design completion - December 2014
      Substructure start - January 2015
      Substructure complete - December 2016
      Electric construction start - January 2017
      Pole removal complete - December 2018

    3. Vistamont Utility Underground District No. 35A

      Assessment Process Start - TBD
      Assessment Public Hearing - TBD
      Assessment Process Complete - TBD
      Design start - TBD
      Design completion - TBD
      Substructure start - TBD
      Substructure complete - TBD
      Electric construction start - TBD
      Pole removal complete - TBD

     

  2. Status of Applicant Financed Underground Utility Districts

Applicant Financed Underground Utility District Informational Packets are currently being revised. They are scheduled to be available at a later date.

The moratorium on applications for Utility Underground District will continue indefinitely.