Annual Construction Program
Planned Sanitary Sewer Projects

FY 2015 Capital Improvement and Rehabilitation Projects, subject to change:

Panoramic Way Area - Phase 3
Santa Barbara Road, Northampton Avenue, Southampton Avenue, San Luis Road, Indian Rock Avenue, Oxford Street area
Contra Costa Avenue, Capistrano Avenue area
Dwight Way (Prospect to Telegraph), Piedmont Avenue, Warring Street, Derby Street area
Parker Street (7th to Railroad)/Bayer
5th Street (Cedar to University)
Shattuck Avenue, Shattuck Square, Addison Street
Hearst Avenue (Shattuck to Bonita)
Cedar Street (San Pablo to 5th)
Buena Avenue (McGee to California), North Street (Dead end to Jaynes), Jaynes Street (Edith to California), Comstock Court (Jaynes to Dead end), Vine Street (Edith to McGee)
FY 2015 Manhole Rehabilitation at various locations

Emergency Projects:

Sanitary Sewer emergency repairs will be performed at several locations throughout the City identified by staff as high priority. Repairs will be made primarily in locations that have recently experienced sanitary sewage overflows, back-ups, clogs, and infiltration, and/or have increasing occurrences of maintenance issues. Such repairs may consist of a temporary patch or pipe replacement.