Translation Disclaimer

Department of Public Works
Department of Public Works

Scheduled Construction Activities
for
Week of April 24, 2017

Detailed information pertaining to construction projects and related activities within the city.

Subscribe to this page to receive e-mail notification when new information is posted

  1. Sanitary Sewer Rehabilitation Projects

    1. Sanitary Sewer Rehabilitation
      Francisco, 5th, Curtis, Delaware, Lincoln, Virginia, Sutter, Henry, Hopkins, and Eunice
      Pacific Trenchless
      Project Notice and Map (.pdf)

      CCTV of sanitary sewer main and laterals on Lincoln, Francisco, Virginia, Sutter, Hopkins, and 5th. Rehabilitate one manhole on Eunice/Shattuck.

      Completed urgent 300’ of sanitary sewer main and 10 laterals to be rehabilitated on Woolsey Street (2300 block). Pressure testing of new sanitary main and laterals to be scheduled.

      rdbarrierNote: Please heed all “No Parking”, temporary directional signs in project area. Please DRIVE SLOW thru the construction area.

    2. Sanitary Sewer Rehabilitation
      Adeline, Shattuck, Haste, MLK, Alcatraz, Ellis, Colusa, Tacoma, Acton, and Channing
      Pacific Trenchless
      Project Notice and Map (.pdf)

      CCTV existing sanitary sewer mains and laterals throughout the project area.

      Continue rehabilitation of sanitary sewer main and laterals on Adeline Street (2700 to 2900 block) from Ward to Ashby.

      Continue rehabilitation of sanitary sewer main and laterals on Channing Way (1500 to 1700 block) from Sacramento to Grant.

      Continue rehabilitation of sanitary sewer main and laterals on Alcatraz Avenue (1700 block) from King to Adeline.

      Restoration work of concrete and asphalt paving throughout the project areas that were disturbed during construction will also be scheduled.

      Underground service alert (USA) marking to be accomplished by utility companies. Potholing of existing underground utilities that may be in conflict with new installation of sewer main and laterals.

      rdbarrierPlease obey all “No Parking” signs posted with the construction area. Drive “SLOWLY” through the active construction site and “HEED” all temporary traffic and flagman directions.

    3. Sanitary Sewer Rehabilitation
      M. L. King, Vine, Jefferson, Bancroft, Milvia, Spruce Backline, La Loma and Vincente Backline
      Andes Construction
      Project Notice and Map A   Project Notice and Map B

      Continue CCTV existing sanitary sewer mains and laterals throughout the project area.

      Continue rehabilitation of sanitary sewer main and laterals on Bancroft Way (2000 block) from Milvia to Shattuck.

      Continue rehabilitation of sanitary sewer main and laterals on Martin Luther King Jr. Way (1600 to 1900 block) from Virginia to Vine.

      Continue rehabilitation of manholes throughout project area.

      Urgent Work: Contractor to construct new lift station and force main for Berkeley Animal Shelter located on Bolivar Drive. Work to include west end of Addison Street and west of 2nd Street.

      rdbarrierPlease obey all “No Parking” signs posted with the construction area. Drive “SLOWLY” through the active construction site and “HEED” all temporary traffic and flagman directions.

    4. Sanitary Sewer Rehabilitation
      Thousand Oaks Blvd and Backline, Colusa Ave and Backline, Vincent Ave Backline, Santa Rosa Ave Backline Ensenada Ave, San Pedro Ave Backline, The Alameda Backline, Tulare Ave, Modoc St, Tenth St, San Pablo Ave, Virginia St, Seventh St, and 1003 Overlook Rd Backline
      Mosto Construction
      Project Notice and Map (.pdf)

      Upcoming project.

    5. Sanitary Sewer Rehabilitation
      Virginia Street, 5th Street, 6th Street, 10th Street, Belvedere Avenue, Oxford Street, San Diego Road, Laurel Lane, Milvia Street, Walnut Street and Backline, Murray Street, 7th Street,66th Street, Idaho Street, Harmon Street and Boise Street
      Andes Construction, Inc.
      Project Notice and Map (.pdf)

      Upcoming project.

  2. Street Paving Projects

    1. Street Rehabilitation FY 2016
      9th, Belrose, Campus, Claremont Blvd, Codornices, Derby, East Parnassus Ct, Hawthorne Terrace, Heinz, Hilgard, Parker, Piedmont, Piedmont Crescent, Rose, Spruce, Virginia, Warring, West Parnassus Ct
      Granite Rock Company
      Project Notice (.pdf)
      E-mail link to Project Engineer   E-mail link to Project Inspector

      Monument punching throughout the project area.

    2. Street Rehabilitation FY 2017
      Bancroft, The Alameda, Tulare, Contra Costa, Solano
      Gallagher & Burk, Inc.
      Project Notice (.pdf)
      E-mail link to Project Engineer

      Upcoming project.

  3. Storm Drainage Projects

    1. FY 2016 Drainage and Valley Gutter Improvements
      6th/Hearst, Curtis/Francisco, Jones/10th, Stuart/California, Bancroft/Bolivar, and 1060 Cragmont Ave east of Regal Road
      Sposeto Engineering
      Project Notice (.pdf)
      E-mail link to Project Engineer   E-mail link to Project Inspector

      rdbarrierPaving at Stuart and California. 24-hour intersection closure and detour will be put into place on Monday, April 24th.

      Storm drain infrastructure renewal at 6th/Hearst.

      Layout at Cragmont/Regal.

  4. Transportation Projects

    1. Hearst Avenue Complete Street Project
      Hearst Avenue from Henry to La Loma, Oxford Street from Hearst to 160' North of Hearst, and Le Roy Avenue from Hearst to 225' North of Hearst
      Ray's Electric
      E-mail link to Project Engineer   E-mail link to Project Inspector

      Installation of storm drain/irrigation pipe and backfill at bio-retention basin at SE corner Oxford/Hearst.

      Trenching and boring irrigation lateral on south side of Hearst between Oxford and Arch.

      ADA curb ramp upgrade work at NW Walnut/Hearst, NE & NW Oxford/Hearst, SW Le Roy/Hearst.

      AB placement, formwork, and concrete pour at north side of Hearst between Oxford/Spruce.

      Storm drain work and pedestrian railing installation on south side of Hearst west of Arch.

      AB placement, formwork, concrete pour, and asphalt paving at south side of Hearst between Le Conte and Euclid.

      Storm drain work, roadway excavation/concrete demo, subgrade preparation, AB placement/compaction, formwork, concrete pour at south side Euclid/Hearst.

      Excavate and pour foundations for new traffic signal poles at Hearst/Le Roy and at Hearst/Arch.

  5. Other

    1. Flare Station Replacement and Well Field Upgrades
      11 Spinnaker Way, Cesar Chavez Park
      Innovative Construction Solutions
      E-mail link to Project Engineer   E-mail link to Project Inspector

      PG&E meter relocation pending.

    2. Waste Transfer Station Pavement Rehabilitation Project & Water Treatment Systems Project
      1201 Second St
      O.C. Jones & Sons
      Public Notice
      E-mail link to Project Manager

      Punchlist work. Additions to tank discharge pipes and flow meters.

  6. Parks Projects

      For information on Parks projects, please visit the Parks Recreation & Waterfront Department.

    1. Berkeley Rose Garden
      1201 Euclid Avenue
      HM Construction
      Project Notice  Postcard

      Access May Be Restricted During Construction, see signs posted at the site.
      Trellis – Closed During Construction
      Tennis Court 3 (near restroom) – Planned to remain open during construction*
      Tennis Court 2 (next to Court 3) – Planned to remain open during construction*
      Practice Tennis Court – Planned to remain open during construction*
      Tennis Court 1 (northwest corner of the site) – Closed During Construction*
      Tunnel to/from Codornices Park – Closed During Construction
      Restroom – Access limited during construction

      Anticipated re-opening in May 2017.

      *Tennis Courts closed for maintenance on 3/27/2017. Anticipated re-opening April 14th. Please see signs posted at the site.

    2. Grove Park
      2828 Martin Luther King Jr. Way
      Integra Construction Services
      Project Notice   Postcard 

      Tennis Courts – will be Closed During Construction
      Basketball Courts – will be Closed During Construction
      Restrooms – will be Closed During Construction
      Ball field and dugout areas – will remain open, however the area with the viewing bleachers are closed during construction.

      Other areas of Grove Park, including the Recreation Center, will not be affected and are planned to remain open.

      Anticipated re-opening in July 2017.

    3. James Kenney Community Center Seismic Retrofit
      1720 8th Street
      B Bros Construction
      E-mail link to Project Engineer

      Seismic retrofit and re-siding work.

      Please be advised that the building facilities will be closed for the project duration. The tennis courts and park will remain open during daylight hours.

    4. Berkeley Skate Park Repair
      Corner of Harrison Street and 5th Street
      Greenwald Builders
      Closure Notice

      The project consists of the repair of six separate features of the park; the transition ramp, the rollover on the north side of the park, the pump mound, the wall at bowl ledge at west side of park, the flat bar in the north east area of park, and reconstruction of metal coping on edges located in center and north side of the park. The Skate Park is anticipated to be closed for approximately 8 weeks. Construction is in progress.

    5. Willard Park Play Area and Pathway Renovation
      2720 Regent Street
      Redwood Engineering Construction

      Upcoming Project to begin on or after 4/24/2017. Tot playground and pathway between tot playground and tennis courts will be closed during renovation. Tennis courts will remain open during daylight hours with modified access on the west side of the courts. Ball wall and practice court area will be closed for staging during construction.

  7. Outside Agency Projects

    1. PG&E
      E-mail link to City contact person

      rdbarrierSacramento Street between Cedar and Rose - Installation of new gas main and services.

      Numerous AC restoration, concrete restoration and pole replacement in small areas throughout the City.

      Claremont at Hillcrest - SCADA installation.

    2. EBMUD
      E-mail link to City contact person

      Virginia Street from Sacramento to Spruce - Installation of new 8" water main and services pending.

      Grant Street from Virginia to Rose - Installation of new water main and services pending.

      Delaware Street between Shattuck and Walnut - Installation of new main and services pending.

      Euclid Avenue between Keith and Crystal - Installation of new main, services and fire hydrants. Paving pending.
      Link to EBMUD's Euclid Avenue Pipeline Replacement webpage.

      7th Street from Virginia to Delaware - Water main replacement. Restoration paving pending.
      Link to EBMUD's 7th/Delaware Pipeline Replacement webpage.

      Restoration work at numerous small areas throughout the city.

      Berkeley View Facility Upgrade
      SE corner of Shasta Road and Hill Road (next to Fire Station #7 on Shasta Road)
      EBMUD Community Affairs Office, (510) 287-0140, lluong@ebmud.com
      After hours, 1 (866) 403-2683
      EBMUD Public Notice (.pdf)
      EBMUD Public Notice - June 2015 Update (.pdf)

      Replacement of existing pumps, motors, electrical components and internal cranes. Contractor will be using the Shasta Reservoir property at the end of Bay Tree Lane for staging and parking.

      For updated information and contacts regarding EBMUD Reservoir Replacement and Transmission Pipeline projects please follow the appropriate link below:

      Panoramic Hill Improvements
      EBMUD pipeline replacement on the Oakland side of Panoramic Hill began in July 2016. Berkeley Panoramic Hill pipeline and service replacement scheduled to begin in April 2017. Helicopter delivery of pipe scheduled for April 27, 2017, 9AM to 4PM. In case of weather, the helicopter delivery operation will take place on May 3rd. Starting May 10th, road closures on Panoramic are currently anticipated during working hours through July 2017.
      EBMUD April 2017 Helicopter Delivery Notice (.pdf)

      Summit Reservoir Replacement Project (Spruce at Grizzly Peak)
      Vassar (approximately at 417 Vassar) - Work on Vassar Ave. will continue through the spring for the new inlet/outlet line to the reservoir. Expect temporary road closures on Vassar to through traffic during work activity and loss of some street parking. Please heed no parking signs and allow a few additional minutes for travel.

      Once the project is nearing completion, new landscaping will be placed within the Summit Reservoir site and the temporary tank will be removed. A walking path will also be added along Grizzly Peak. The project is expected to be completed by the end of 2017.

      EBMUD Summit Reservoir Notice - December 2014 (.pdf)
      Summit Reservoir Update Notice - October 2015 (.pdf)

      Wildcat Pipeline Project

    3. AT&T Telephone
      E-mail link to City contact person

      Crews removing old poles throughout Berkeley.
      Investigative and cable pulling work within existing manholes and vaults throughout the city.

    4. Paxio
      E-mail link to City contact person

      Contractor performing aerial fiber work at 7th from Ashby to Grayson, 8th from Ashby to Grayson, 9th from Ashby to Grayson and 10th from Ashby to Grayson.

    5. Caltrans
      Ashby Avenue between Shattuck Avenue and 7th Street
      Caltrans Contact: Shannon Brinias, (510) 286-5543 or Chiconda Davis, (510) 286-1227

      Caltrans working at various locations on Ashby Avenue upgrading curb ramps and sidewalks.

      Link to Caltrans project webpage - ADA Compliance Curb Ramps and Sidewalk Improvements on State Route 13/Ashby Avenue

    6. University of California at Berkeley
      Information provided by UC contact person:
      Christine Shaff
      UC Berkeley Real Estate, (510) 643-4793

      Berkeley Way West
      Construction of a new academic building is underway in the lot bounded by Berkeley Way, Shattuck Ave and Hearst Ave. The building will house the School of Public Health, School of Education, and Department of Psychology. Ground floor retail along Shattuck Ave. is also planned. Construction is scheduled to continue through late 2017.

      Bancroft Residence Hall Project
      The Bancroft Residence Hall project will bring new student housing to Bancroft Way along with retail and new space for Stiles Hall. The project, bounded by Bancroft Way, Dana St, and Durant St. includes beds for 775 students along with study and activity space. More about the Bancroft Residence Hall project, including a link to a webcam, is online at http://realestate.berkeley.edu/bancroft-residence-hall-student-housing-project. The new housing is scheduled to open in August 2018.

      Information about campus construction is available on the web at realestate.berkeley.edu. Questions or concerns can be addressed to Christine Shaff, UC Berkeley Real Estate, at (510) 643-4793 or cshaff@berkeley.edu. Other campus resources include the UC Office of Environment, Health and Safety at (510) 642-3073.

In all construction areas:

  • Please observe all "NO PARKING" signs
  • Tie or keep pets away to assure both pet and worker safety
  • Keep children out of work area
  • Dust and noise will be prevalent, please take proper precautions

If you did not find the project you were looking for, it may have moved to the Recently Completed Projects page.

Recently completed sanitary sewer projects

Recently completed storm drain projects

Recently completed street rehabilitation projects

Recently completed sidewalk and pathway projects

 

Home | Web Policy | Text-Only Site Map | Contact Us
Department of Public Works, 2180 Milvia Street, Berkeley, CA 94704
Questions or comments? Email: publicworks@cityofberkeley.info Phone: (510) 981-6300
(510) 981-CITY/2489 or 311 from any landline in Berkeley
TTY: (510) 981-6903
###